Most of this site's guides go deep on one part of an electric boat: the motor, the battery, the cabling, the charger. This one is the order to do it all in. Each step says what to decide, what can go wrong, and where the detail is.
It's written for a displacement sailboat or launch replacing a diesel inboard or saildrive — the boats our calculator is built for. Whether you install it yourself or hire a yard, the steps are the same; the difference is who does them.
Step 1: decide whether electric suits you
Before anything else, be honest about how you use the boat. Electric is strongest when you motor in and out of harbour, through calms and onto a mooring, and you charge at your berth; it is weakest when you motor for long hours on passage with nowhere to charge. The electric vs diesel guide sets out both cases and an eight-question checklist; the savings calculator and payback calculator put numbers on the money side, which at leisure hours rarely makes the case on its own.
Step 2: measure the boat and your motoring
The sizing is only as good as these inputs:
| What | Where to get it | Why it matters |
|---|---|---|
| Waterline length | builder's data, class association, or measure it | sets hull speed, and so how fast power climbs |
| Displacement as you sail her | builder's data plus your gear, water and crew | power is roughly proportional to weight |
| Drive type | shaft or saildrive | a saildrive needs a little more power, and decides which motors fit |
| The speed you actually motor at | your log or GPS, not the old engine's top speed | the biggest single input to pack size |
| Hours of motoring on a typical day | your logbook | sets the battery energy |
| Charging at your berth | the pedestal's amps and voltage | sets the charger and how fast you refill |
Builders' brochure displacements are often the light figure; a cruising boat with tanks, gear and stores is heavier. Use the weight you actually sail at. If you have a battery monitor already, measure your hotel loads too — they come out of the same pack.
Step 3: size the system
Put those figures into the calculator. It gives the motor power, pack size, DC and phase current, cable size and charge time, and the guides explain each:
- Motor power: how many kW a sailboat needs — and why trying your target speed a tenth of a knot lower can drop a whole motor size.
- Battery: battery sizing for range and range planning.
- Voltage: 48 V vs 96 V — the current at 48 V decides it.
- Currents: DC current vs phase current — which figure sizes which part.
- Cabling: cable sizing.
The calculator's power curve is an estimate: see how accurate it is, and use the reserve it adds rather than trimming it.
Step 4: choose the architecture
Four decisions, in this order, because each constrains the next:
- Packaged drive or separate motor and controller. A packaged drive comes with its controller matched by the maker; separate parts make matching the controller's continuous current your job. At 48 V, separately sourced controllers run out of rating at roughly 6–10 kW of continuous motor. See the motor and controller guide.
- Keep the drive type the hull has. A saildrive opening takes an electric saildrive, and a shaft takes an electric shaft motor; changing between them is structural hull work. See saildrive vs shaft drive.
- The battery system. A vendor's integrated system (such as Victron's Lithium NG with the Lynx Smart BMS NG) or modules with a separate master BMS. Check the BMS's current rating against your DC current, and whether the system reaches your voltage. See battery bank capacity and wiring and the BMS guide.
- Charging and monitoring. A shore charger sized between the battery's limit and the pedestal, solar if you have the area, and a system controller that makes them work together. See chargers and inverters, shore power, solar and DVCC.
Check also that the propeller suits the new drive's shaft speed — usually it won't be the diesel's. See the propeller guide.
Step 5: budget and quotes
Price the complete system, not the motor and battery alone. The repower cost guide prices one system from a maker's published list and lists everything else to get quoted: cabling, fuse, contactor, isolator, charger, propeller, battery compartment, labour, commissioning. Send installers the calculator's figures as the specification, so every quote prices the same thing.
Step 6: insurance and the rules — before you start
Your insurer. Ask what they need to keep covering the boat after the conversion: who may do the work, documentation, an inspection or survey. A technically sound DIY installation can still be hard to insure if you ask afterwards.
In the EU and EEA: is it a major craft conversion? The Recreational Craft Directive (2013/53/EU) defines a major craft conversion as a conversion that "changes the means of propulsion of the watercraft", involves a major engine modification, or alters the craft so it may no longer meet the Directive's essential requirements (Article 3(7)). Under Article 19(3), anyone who places on the market or puts into service a watercraft "after a major modification or conversion" must first apply the post-construction assessment procedure of Article 23 — and under Annex V, the person doing it takes responsibility for the craft's conformity, as a manufacturer would for a new boat.
How that applies to an owner replacing a diesel with an electric motor is not settled in practice. In October 2025 the European Boating Association noted that market surveillance authorities and notified bodies have been drawing up lists of what does and doesn't count, and argued that post-construction assessment should be limited to cases where a boat "is in essence a new watercraft". So ask your national authority, or a notified body for recreational craft, before you start, and keep the answer in writing. The UK's Recreational Craft Regulations 2017 use the same definition.
Elsewhere, check your national rules, and plan to follow the recognised standards — ABYC E-11 and E-30 in the US, ISO 16315 for electric propulsion on small craft internationally. The DC safety guide lists them.
Step 7: remove the diesel — and everything that served it
Removing the engine is the easy part. What it leaves behind needs decisions:
- Fuel system. Drain the tank and lines, and dispose of the fuel and engine oil as your marina or local rules require. Remove the tank if you can — it frees space for batteries — or clean it and seal the filler and vents so nobody fills it by mistake.
- Exhaust. Remove the exhaust hose, water-lift muffler and the exhaust through-hull.
- Raw-water cooling. If the electric drive doesn't use the old raw-water intake, remove the seacock and through-hull and close the hole properly, or keep it fitted, closed and serviceable. A forgotten seacock is still a hole below the waterline.
- Engine beds and saildrive opening. A shaft motor usually reuses the beds, perhaps with an adapter. On a saildrive boat, electric saildrives are made to use the existing opening: Oceanvolt, for example, says its SD saildrives fit "directly onto existing Volvo Penta and Yanmar saildrive beds". Confirm the fit for your hull with the maker.
- The old 12 V system. The diesel's alternator charged the 12 V bank. Plan what replaces it — usually a DC-DC converter from the propulsion bank — before the alternator leaves the boat.
Step 8: plan for weight and trim
Taking out an engine, gearbox and a tank of fuel, then putting in a battery bank, moves weight around. Before removing anything, mark the waterline fore and aft, or photograph it against a fixed reference, so you can compare afterwards.
The numbers to compare:
- Out: the engine and gearbox (dry weight from the engine manual), plus fuel — diesel weighs roughly 0.84 kg a litre, so a full 100-litre tank is about 84 kg — plus exhaust parts, coolant and starter battery.
- In: the battery bank, motor, controller, cabling and charger. Batteries dominate: Victron's 51.2 V, 5.12 kWh Lithium NG weighs about 37 kg, so the calculator's 25.6 kWh pack for a 35-footer is about 185 kg in batteries alone.
Put the batteries low, near the centreline, and close to where the engine and fuel tank were, so the change in trim is as small as possible. If the bank is much heavier than what came out, or has to go far from the old engine position, ask a naval architect or the builder about trim and stability before you build the battery boxes.
Step 9: install in a planned order
The DC safety guide explains each protective part; this is the order that keeps you safe while you work:
- Battery compartment first. Dry, ventilated, above the bilge water, with the batteries restrained so they can't move in a knockdown. See the LiFePO₄ guide.
- Motor and drive. Mount, align the shaft or fit the saildrive, fit the propeller, and connect cooling if the motor or controller needs it.
- Main DC path, with the batteries disconnected. Class T fuse close to the battery positive, manual isolator, BMS-controlled contactor, pre-charge, then the cables to the controller — short, run together, crimped with the right die and torqued to the maker's figures.
- Control and communication. BMS to controller (CAN, or the BMS's allowed-to-discharge signal), throttle, key switch, display, and the system controller if you have one.
- Charging. Shore inlet, galvanic isolator or isolation transformer, charger, solar controller, and the DC-DC converter for the 12 V house supply.
- Check before energising. Polarity, every lug's torque, fuse ratings, that nothing chafes, and that the isolator really isolates. Have a qualified marine electrician inspect a DIY installation at this point, before the batteries are connected.
Step 10: commission at the dock
With the boat securely moored, springs on:
- Battery and BMS. Charge and voltage limits set from the battery maker's figures; pre-alarm and disconnect working; the BMS stops charging and discharging when it should.
- Charging. Shore charging at the expected current, within the pedestal's limit; solar charging; with a system controller, total charge current within the battery's limit — see the DVCC guide.
- Motor. Forward and reverse at low power in gear; then more power, watching battery current, controller and motor temperatures and any fault codes. Check that the low-battery sequence — warning, then power reduction or disconnect — happens as designed.
- A baseline. Record the sound, DC current and temperatures at three steady speeds, so later changes stand out. The noise diagnosis guide explains how and why.
Re-check lug torque and shaft alignment after the first few hours of running.
Step 11: sea trial and measure
On a calm day, run at three or four steady speeds, each both ways on the same course, and note the GPS speed and the battery power at each. Average the two directions to cancel wind and tide. Compare with the calculator's prediction for your boat, and use what you measure — not the estimate — for range planning from then on.
If you send your figures to our owner reports page, they're published next to the calculator's prediction, which is how the calculator gets checked on boats like yours.
The order, at a glance
| Step | Decide or do | Detail |
|---|---|---|
| 1 | Does electric suit how you use the boat? | Electric vs diesel |
| 2 | Measure the boat and your motoring | — |
| 3 | Size motor, battery, voltage, current, cable | Calculator |
| 4 | Drive, battery system, charging, propeller | Motors, BMS |
| 5 | Budget and quotes | Repower cost |
| 6 | Insurer, and the rules where you are | above |
| 7 | Remove the diesel and its systems | above |
| 8 | Weight and trim | above |
| 9 | Install in order | DC safety |
| 10 | Commission at the dock | DVCC |
| 11 | Sea trial and measure | Owner reports |
Sources
Checked on 15 November 2026:
- Directive 2013/53/EU on recreational craft: Article 3 definitions (propulsion engine, major engine modification, major craft conversion, means of propulsion, placing on the market, putting into service) and Article 19 (post-construction assessment after a major conversion); official text also on EUR-Lex
- European Boating Association — Statement on the Recreational Craft Directive and Major Craft Conversions, October 2025 (copy hosted by the Finnish sailing and boating federation): lists being drawn up by authorities and notified bodies, owner's responsibility under Annex V, the association's position
- Victron Energy — Lithium NG batteries datasheet: energy and weight of the 51.2 V battery
- Oceanvolt — SD saildrives: fit to existing saildrive beds
- Diesel density: EN 590 road diesel is specified at 820–845 kg/m³ at 15 °C; marine gas oil is similar
- The calculator's sizing model: the 35-footer's pack
Related reading
- Electric vs diesel repower — whether to convert at all
- Electric boat repower cost — what to get quoted
- Electric boat DC-side safety — the protective parts, and the standards
- Repower guides by boat type — sized examples for six common boats
Want exact numbers for your boat?
Use the configurator to generate a vendor-ready spec sheet.
Start the configurator